Florence Avenue Interchange Project – Week of Apr. 20 – Apr. 27, 2018

This project is 64% complete.
Projected date of completion for the Florence Ave. Bridge: *Updated to December of 2019.
Project date for completion of project: Late 2019. 

 

Contractor removing weeds along Longworth Ave. southwest of I-5 and the Florence Ave. Bridge (below):

 

Crane lifts and places concrete mold into place on rebar frame of retaining wall on west side of I-5 (below):

 


 

Crews continue to back-fill and grade area along retaining wall on east side of I-5 (below):


 

 