FLORENCE AVENUE INTERCHANGE PROJECT – Week of December 13, 2015

Crews are working to form soundwalls along northbound and southbound I-5. Work is also underway to construct a section of temporary pavement along northbound I-5.

Shoring activity is still underway along the Orr and Day railroad bridge, which passes underneath the I-5 freeway. This work will take place weekdays (Monday through Friday) between 6:30 a.m. and 3 p.m. and will be ongoing for approximately the next three to four weeks.

 

 

 