Florence Avenue Interchange Project – December 14 – December 21, 2018

This project is 73% complete.
Projected date of completion for the Florence Ave. Bridge: Early 2020.
Project date for completion of project: Early 2020. 

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

We have started pouring the final layer of concrete for the new lanes that we are adding to I-5 at Florence Ave. on the east side of the freeway. Photos below from December 11:

 

The contractor shifted southbound traffic on I-5 south of the Florence Ave. Bridge to the new lanes in the median on the night of September 30.  Then northbound lanes were shifted to the median lanes on the night of October 11. Photos below show before and after the lane shifts:

 