Florence Avenue Interchange Project – December 7 – December 14, 2018

This project is 73% complete.
Projected date of completion for the Florence Ave. Bridge: Early 2020.
Project date for completion of project: Early 2020. 

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

Grading and compacting of earth continue as we build new freeway lanes on the right shoulders of both directions of I-5 from south of Florence Ave. to I-605. Local residents may experience vibration, shaking, and noise as we grade and compact the new roadway. The next step will be to pour concrete. Photos below from October 30, November 13, and November 20:

 

The contractor shifted southbound traffic on I-5 south of the Florence Ave. Bridge to the new lanes in the median on the night of September 30.  Then northbound lanes were shifted to the median lanes on the night of October 11. Photos below show before and after the lane shifts:

 