Florence Avenue Interchange Project – January 18 – January 25, 2019

This project is 75% complete.
Projected date of completion for the Florence Ave. Bridge: Early 2020.
Project date for completion of project: Early 2020. 

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

Work was suspended for most of this past week due to rain. 

We are pouring concrete for the new lanes that we are adding to both sides of I-5 near the Florence Ave. Bridge. Photos below from January 2 and January 8:

 

Workers completed installing “piles” for the retaining wall for the future Florence Ave. on ramp to northbound I-5. Piles are steel beams installed vertically below ground to provide structural support. Photos below from January 8:

 

 