Crews are working to form soundwalls along northbound and southbound I-5. Roadway excavation is underway behind k-rail and the construction fencing, along Mondon Avenue between Cecilia Street and Buell Street. Over the next few weeks crews will be pouring concrete for the new soundwall adjacent to southbound I-5. This work will be conducted weekdays (Monday through Friday) between 6:30 a.m. and 3 p.m. and will be ongoing for approximately the next two to three weeks.
Shoring activity is still underway along the Orr and Day railroad bridge, which passes underneath the I-5 freeway. This work will take place weekdays (Monday through Friday) between 6:30 a.m. and 3 p.m. and will be ongoing for approximately the next three to four weeks.
.