Florence Avenue Interchange Project – Week of May 25 – June 1, 2018

This project is 67% complete.
Projected date of completion for the Florence Ave. Bridge: *Updated to December of 2019.
Project date for completion of project: Late 2019. 

You may also go to our Twitter page at twitter.com/My5LA for project updates.

The connector ramps from northbound I-5 to northbound and southbound I-605 have been reconfigured to one lane up to the overpass, then opening up to two lanes. This will allow necessary work space near the retaining walls.

Workers constructing the deck of the Orr & Day Bridge over the railroad tracks beneath northbound I-5 south of the Florence Avenue Bridge (below):

 

The future Florence Ave. on ramp to NB I-5 (below):

 

The current phase of construction will focus on completing retaining walls and traffic barriers on both sides of I-5 north of the Florence Ave. Bridge. (below):

 

A view of I-5 on the north side of the Florence Ave. Bridge (below):

 

 