FLORENCE AVENUE INTERCHANGE PROJECT – Week of September 18, 2016

Crews have resumed pile driving activity along northbound I-5 at Florence Avenue. Work will be conducted weekdays, between 7 a.m. and 3:30 p.m. and will be ongoing intermittently for the next four to six weeks. Please be advised that this work may be loud and disruptive due to equipment noise, vibration and pounding related to pile driving activity.

Crews are continuing daytime work on the cul-de-sacs along Dollison Drive in the City of Downey. This work will take place intermittently between 7 a.m. and 3:30 p.m., Monday through Friday for approximately two weeks.

Work on the drainage system on Longworth Avenue has been postponed. Residents in the vicinity of this work will be notified once the new start date is scheduled.

Crews are working to form soundwalls along northbound and southbound I-5. Roadway excavation is underway behind k-rail and the construction fencing, along Mondon Avenue between Cecilia Street and Buell Street. Over the next few weeks crews will be pouring concrete for the new soundwall adjacent to southbound I-5. This work will be conducted Monday through Friday between 6:30 a.m. and 3 p.m. and will be ongoing for the next one to two weeks.

Finally, work is ongoing on the Orr and Day railroad bridge, which runs perpendicular to I-5, underneath the freeway, south of Florence Avenue.