I-5 Corridor Improvements – SR-134 to Buena Vista Street, Feb. 16-19, 2016

No Holiday Closures: There will be no construction closures on Presidents Day, Monday, February 15, 2016.

Construction activities and closures listed below are subject to change. Work will occur during daytime hours unless otherwise noted.

Illegal dumping is a crime. Violators will be prosecuted. If you notice illegal dumping at a construction site, get the license plate number and call 911.

➤ CONSTRUCTION ACTIVITIES for February 16-19, 2016

SR-134 to Magnolia Boulevard

Bridge Construction: Work on Sonora Avenue, Alameda Avenue and Western Avenue Bridges. Placement of mulching materials on slopes.

Magnolia Boulevard to Buena Vista Street

Buena Vista Bridge (Winona Bridge): Form and pour soffit and stems (lower part of bridge structure) for southbound I-5 widening.

Buena Vista Railroad Bridge: Form and pour median pier footings and abutments (supporting structures at the ends of the bridge span).

Buena Vista Ramps: Form and pave shoulder.

Empire Avenue: From and pour underpass abutment walls and pier. Retaining wall work.

Railroad Retaining Wall: Installation of precast wall panels between Hollywood Way and Burbank Boulevard.

Victory Place: Forming of abutments for the bridge and walls.

Old San Fernando Road Tunnel: Concrete crushing and storm drain work.

Utility Work: Conduit work on Victory Place between Empire Avenue and Maria Street. Flaggers will direct motorists.

➤ CLOSURES for February 16-19, 2016

No Holiday Closures: There will be no construction closures on Presidents Day, Monday, February 15, 2016.

SR-134 to Magnolia Boulevard

+ The Los Angeles River Bike Path between Riverside Drive and just south of the SR-134 overcrossing in the City of Los Angeles will be closed through spring 2016. A signed detour is posted that directs bike path users to Zoo Drive and Western Heritage Way. See map here.

Magnolia Boulevard to Buena Vista Street

+ Buena Vista Street closures between San Fernando Boulevard and Winona Avenue:

  • Day closures: Intermittent lane closures in both directions from 9 a.m. to 3 p.m. The street will remain open to motorists.
  • Night closures: Intermittent full street closures in both directions from 10 p.m. to 6 a.m. Detours will be posted.

+ Intermittent closure of the southbound I-5 Burbank Boulevard off-ramp for equipment loading (night work).

Click HERE to see these closures on an interactive map.

Print Friendly, PDF & Email