Buena Vista Street closures between San Fernando Boulevard and Winona Avenue—Monday, February 8th, through Friday, February 12th:
- Day closures: Intermittent lane closures in both directions from 9 a.m. to 3 p.m. The street will remain open to motorists.
- Night closures: Intermittent full street closures in both directions from 10 p.m. to 6 a.m. Detours will be posted.
Construction activities and closures listed below are subject to change. Work will occur during daytime hours unless otherwise noted.
Illegal dumping is a crime. Violators will be prosecuted. If you notice illegal dumping at a construction site, get the license plate number and call 911.
➤ CONSTRUCTION ACTIVITIES for February 4-12, 2016
SR-134 to Magnolia Boulevard
Bridge Construction: Work on Sonora Avenue, Alameda Avenue and Western Avenue Bridges. Placement of mulching materials on slopes.
Magnolia Boulevard to Buena Vista Street
Buena Vista Bridge (Winona Bridge): Forming soffit and stems (lower part of bridge structure) for southbound I-5 widening.
Buena Vista Railroad Bridge: Forming of median pier footings and abutments (supporting structures at the ends of the bridge span).
Buena Vista Ramps: Shoulder paving.
Empire Avenue: Pouring and forming underpass abutment walls and pier. Retaining wall work.
Railroad Retaining Wall: Installation of precast wall panels between Hollywood Way and Burbank Boulevard.
Victory Place: Forming of abutments for the bridge and walls.
Old San Fernando Road Tunnel: Concrete crushing and storm drain work.
Utility Work: Conduit work on Victory Place between Empire Avenue and Wilson Avenue. Flaggers will direct motorists.
➤ CLOSURES for February 4-12, 2016
SR-134 to Magnolia Boulevard
+ The Los Angeles River Bike Path between Riverside Drive and just south of the SR-134 overcrossing in the City of Los Angeles will be closed through spring 2016. A signed detour is posted that directs bike path users to Zoo Drive and Western Heritage Way. See map here.
Magnolia Boulevard to Buena Vista Street
+ Buena Vista Street closures between San Fernando Boulevard and Winona Avenue—Monday, February 8th, through Friday, February 12th:
- Day closures: Intermittent lane closures in both directions from 9 a.m. to 3 p.m. The street will remain open to motorists.
- Night closures: Intermittent full street closures in both directions from 10 p.m. to 6 a.m. Detours will be posted.
+ Intermittent closure of the southbound I-5 Burbank Boulevard off-ramp for equipment loading (night work).