I-5 Corridor Improvements – SR-134 to Buena Vista Street, Jan. 14-21, 2015

Upcoming Closure: Saturday, Jan. 23, at 3 a.m. to Sunday, Jan. 24, at 6 p.m., Buena Vista Street will be closed in both directions between Winona Avenue and San Fernando Boulevard for bridge work. Signed detours will be posted.

Construction activities and closures listed below are subject to change. Work will occur during daytime hours unless otherwise noted.

Illegal dumping is a crime. Violators will be prosecuted. If you notice illegal dumping at a construction site, get the license plate number and call 911.

➤ CONSTRUCTION ACTIVITIES for January 14-21, 2016

SR-134 to Magnolia Boulevard

Alameda Avenue: Construction of concrete bridge barriers.

Alameda Avenue Northbound and Southbound I-5 Ramps:  Constructing drainage inlets.

Bridge Construction: Work on Sonora Avenue, Alameda Avenue and Western Avenue Bridges.

Magnolia Boulevard to Buena Vista Street

Buena Vista Bridge (Winona Bridge): Installation of falsework on southbound side. Work on lower part of bridge structure (forming soffit and stems) for southbound I-5 widening.

Buena Vista Railroad Bridge: Forming of abutment footings and abutments (supporting structures at the ends of the bridge span).

Buena Vista Ramps:  Paving operation between the ramps.

Empire Avenue: Pouring and forming footings for underpass and abutment walls. Retaining wall work.

Railroad Retaining Wall: Installation of precast wall panels between Hollywood Way and Burbank Boulevard.

Victory Place: Forming of abutments for the bridge and walls.

Old San Fernando Road Tunnel: Concrete crushing.

Utility Work:  Underground utility work on Victory Place at Maria Street.  Flaggers will direct motorists.


➤ CLOSURES for January 14-21, 2016

SR-134 to Magnolia Boulevard

+ Intermittent closures of the northbound I-5 Alameda Avenue off- and on-ramps from 7 a.m. to 3:30 p.m.

+ The Los Angeles River Bike Path between Riverside Drive and just south of the SR-134 overcrossing in the City of Los Angeles will be closed through spring 2016. A signed detour is posted that directs bike path users to Zoo Drive and Western Heritage Way. See map here.

Magnolia Boulevard to Buena Vista Street

 + Intermittent closure of the southbound I-5 Burbank Boulevard off-ramp for equipment loading (night work).