Leland Way Channel Cap: Concrete pour for soundwalls and drilling. Flaggers will be on site to ensure street and driveway access at all times.
Empire Avenue Interchange/Undercrossing: Through the end of April, crews are installing metal plates and beams for shoring on the southbound I-5 shoulder near the old San Fernando tunnel. The work is necessary to construct the new Empire Avenue interchange. Beginning the week of April 6, the operation will switch to daytime hours. Residents may notice some noise and/or vibration while this work is underway.
Lincoln Street/Victory Place Improvements: Signal work. Lincoln Street is now OPEN at Victory Street.
Temporary Railroad Tracks: Drilling and installation of metal plates for the shoring wall needed for the temporary tracks by Empire Avenue. There may be some noise and vibration during both night and daytime hours associated with this work.
Retaining Wall/Soundwall Work (excavation, concrete pours, crushing): Work will occur at the following locations:
Near the southbound I-5 Empire Avenue on- and off-ramps
Old Southbound Scott Road off-ramp
South of Buena Vista Street
On Buena Vista Street between Winona Avenue and San Fernando Boulevard (abutment wall)
Southbound I-5 Buena Vista on ramp
Concrete Recycling: Crushing of concrete near the old Scott Road off-ramp (day and night work).
I-5 Striping: Striping of I-5 (both directions) between Burbank Boulevard and Buena Vista Street (night work).
Two lanes of northbound Buena Vista Street between Winona Avenue and San Fernando Boulevard from 10 p.m. to 6 a.m.
Intermittent daytime closures of one lane northbound Buena Vista Street between Winona Avenue and San Fernando Boulevard.
Up to three lanes of northbound and southbound I-5 between Burbank Boulevard and Buena Vista Street will be closed from 9 p.m. to 6 a.m. Closures will not be implemented in both directions simultaneously. At least one lane will remain open when other lanes are closed. The most restrictive closures (i.e., the most lanes closed) will occur between midnight and 4 a.m.
Workers planting along the shoulder of northbound I-5 at Valley View Avenue in La Mirada. Please #BeWorkZoneAlert. https://t.co/xA5vA0EcPQhttps://t.co/xA5vA0EcPQMarch 9, 2023 7:34 pm
Follow My5LA
Workers have been installing new guardrail along the new Valley View Ave. off-ramp from northbound I-5 in Santa Fe Springs. Please #BeWorkZoneAlert. https://t.co/xA5vA0EcPQhttps://t.co/xA5vA0EcPQMarch 6, 2023 6:01 pm
Follow My5LA
In #Burbank on Saturday 3/4/23 (weather permitting) crews plan to construct colored concrete hardscape here at the SB I-5 Buena Vista on-ramp. Ramp will be reduced to one lane from 7AM-4PM. Project details: https://t.co/kPx9kDocbA @BurbankCA @CHPAltadena @BurbankPD https://t.co/kPx9kDocbAMarch 3, 2023 8:54 pm
Follow My5LA
Check out the weekly update for the I-5 Valley View Ave. interchange project at https://t.co/iaMj2Y3aOJ! Please #BeWorkZoneAlert. https://t.co/iaMj2Y3aOJ!https://t.co/iaMj2Y3aOJ!March 3, 2023 5:42 pm
Follow My5LA
Workers preparing concrete for installation of guardrail along the Valley View Avenue loop off ramp from northbound I-5 in Santa Fe Springs. https://t.co/xA5vA0EcPQhttps://t.co/xA5vA0EcPQFebruary 23, 2023 5:19 pm
Follow My5LA
Workers are installing new guardrail between the mainlines & the northbound Valley View Ave. off-ramp from northbound I-5 in Santa Fe Springs. Please #BeWorkZoneAlert. https://t.co/xA5vA0EcPQhttps://t.co/xA5vA0EcPQFebruary 22, 2023 3:48 pm
Follow My5LA
In #Burbank on eastbound Burbank Blvd at the Southbound I-5 on-ramp, be aware of crews placing concrete at this construction zone this week. Project details: https://t.co/4X5uqMd01v The schedule is subject to change. @BurbankCA https://t.co/4X5uqMd01vFebruary 20, 2023 6:12 pm
Follow My5LA
La Mirada: The contractor has begun constructing curb & gutter along Arbor Place. https://t.co/xA5vA0EcPQhttps://t.co/xA5vA0EcPQFebruary 14, 2023 6:43 pm
Follow My5LA
La Mirada- NB I-5 all lanes scheduled to be closed from Artesia Blvd. to Carmenita Road on-ramp 11 p.m. to 5 a.m. the night of Thursday 2/16 to prepare for final striping & shifting of lanes. WB State Route 91 connector to NB I-5 also closed. Details at https://t.co/lD8pOUBwrKhttps://t.co/lD8pOUBwrKFebruary 14, 2023 4:05 pm
Follow My5LA
In #Burbank, one lane on eastbound Burbank Blvd is temporarily closed at the I-5 bridge for construction of safety enhancements for pedestrians and cyclists. Details: https://t.co/FeWYDc6IXl @BurbankCA #infrastructure https://t.co/FeWYDc6IXlFebruary 13, 2023 11:56 pm
Follow My5LA
Construction Notice Sign Up
Click through to sign up for Timely, Helpful My5LA Info regarding work on the Los Angeles I-5 Freeway Construction Projects.