I-5 NORTH Construction Advisory – SR-134 to Buena Vista Street, February 1-8, 2019

Work will occur during daytime hours unless otherwise noted.

Construction Activities

SR-134 to Magnolia Boulevard

Sonora Avenue, Alameda Avenue, Western Avenue, Providencia Avenue, and LA River Bridges: Crews are working in the I-5 median to widen the bridges.

Providencia Avenue: Crews are installing fence barriers on the pedestrian bridge and constructing the median concrete barrier.

I-5 Median: Crews are installing drainage at night and during the day. Crews are placing concrete pavement at night and constructing the median concrete barrier at night.

Magnolia Boulevard to Buena Vista Street

Northbound I-5 between Burbank Boulevard and Cohasset Street: Northbound traffic will switch to the new pavement on Thursday night/Friday morning, February 7-8, 2019. Lane patterns will change. Crews will be removing pavement in the freeway median. The schedule is weather-permitting and subject to change.

Northbound and Southbound On-Ramps and Off-Ramps at Empire Avenue: Crews are paving the on- and off-ramps and new Empire Avenue.

Closures & Detours

SR-134 to Magnolia Boulevard

Alameda Avenue, Sonora Avenue, Western Avenue and South Flower Street Lane Closures: Intermittent daytime and nighttime street, ramp and lane closures on Alameda Avenue, Sonora Avenue, Western Avenue and South Flower Street through late 2019. Detours are posted.

Northbound and Southbound I-5 Lane Closures: Intermittent northbound and southbound lane closures between 10 p.m. and 6 a.m., at times reducing I-5 to one or two lanes in either direction.

Magnolia Boulevard to Buena Vista Street

Northbound and Southbound I-5 Lane Closures: Intermittent nighttime northbound and southbound I-5 lane closures, at times reducing I-5 to one or two lanes in either direction between Magnolia Boulevard and Hollywood Way from 9 p.m. to 6 a.m.

Buena Vista Street Closures: Intermittent daytime and nighttime closures of Buena Vista Street, in both directions, between San Fernando Boulevard and Winona Avenue.

On- and Off-Ramp Closures: Intermittent on- and off-ramp closures at Buena Vista Street, San Fernando Boulevard and Burbank Boulevard from 9 p.m. to 6 a.m.  Detours will be provided.

 

 