Adoree Street and Frontage Road, have both been opened to through traffic between Imperial Highway and Norwalk Boulevard.
Pile driving activity is underway at Pioneer Boulevard and will be conducted weekdays between 8:30 a.m. and 3:30 p.m.; this work will be ongoing for approximately one more week.
Crews have begun construction of the retaining wall along on Mondon Avenue, between Tina Street and Bayla Street.
Access on Mondon Avenue is temporarily limited to local traffic only, for approximately the next 10 weeks, as crews work to complete improvements in this area. This work will be conducted weekdays between 7 a.m. and 3:30 p.m. For the safety of the public and work crews, “No Through Traffic” signs will be posted on Mondon Avenue at the intersections of Bayla Street and Tina Street.
As crews erect falsework at Imperial Highway and Norwalk Boulevard at I-5, one lane in each direction will be closed at I-5 during the daytime.