IMPERIAL HIGHWAY & PIONEER BOULEVARD PROJECT – Week of January 1, 2017

HOLIDAY CLOSURE SCHEDULE: In observance of the holiday, there will be no closures scheduled on Sunday, January 1, 2017.

On Wednesday, January 4 night crews will switch traffic on southbound I-5 at the Orr and Day bridge beginning at 11 p.m. until 5 a.m. During the traffic switch the southbound I-5 freeway will be closed between the I-605 and Imperial Highway. The southbound and northbound I-605 connectors to southbound I-5 will be closed as well. The closure areas are shown below on the map in red.

DETOUR FROM NORTHBOUND I-605 TO SOUTHBOUND I-5: Motorists will be directed to continue on northbound I-5, exit Lakewood/Rosemead Boulevard off-ramp, continue south on Lakewood Boulevard to access the on-ramp to southbound I-5. The detour route is shown on the map above in green.

DETOUR FROM SOUTHBOUND I-605 to SOUTHBOUND I-5 : Motorists will be directed to continue on southbound I-605 and exit Imperial Highway off-ramp, continue east on Imperial Highway, the south on Frontage Road to access the on-ramp to southbound I-5 . The detour route is shown on the map above in blue.

DETOUR TO CONTINUE ON SOUTHBOUND I-5: Motorists heading southbound on I-5 will be directed to continue on southbound I-605 and exit Imperial Highway off-ramp, continue east on Imperial Highway, then continue south on Frontage Road to access the on-ramp to southbound I-5. The detour is shown on the map above in purple.

Contractor will be performing soundwall work along northbound I-5 south of Norwalk Boulevard along Markdale Avenue. Work will be performed weekdays, between 7 a.m. and 3:30 p.m.

As crews work on Imperial Highway, Norwalk Boulevard and Pioneer Boulevard bridges at I-5, one lane in each direction will be closed on each street (at I-5) during the daytime, between 8 a.m. and 3 p.m.

 

 

 

 

 

 

 

 

 

 