IMPERIAL HIGHWAY & PIONEER BOULEVARD PROJECT – Week of January 3, 2016

HOLIDAY UPDATE: There are no closures scheduled Thursday, Dec. 31 through Sunday, Jan. 3. 

Happy New Year to you and your family on behalf of the I-5 South Corridor Improvements team!

Adoree Street and Frontage Road, have both been opened to through traffic between Imperial Highway and Norwalk Boulevard.

Construction of the retaining wall along Mondon Avenue, between Tina Street and Bayla Street is ongoing.

Access on Mondon Avenue is temporarily limited to local traffic only, for approximately the next 2 months, as crews work to complete improvements in this area. This work will be conducted weekdays between 7 a.m. and 3:30 p.m.

As crews work on Imperial Highway and Norwalk Boulevard bridges at I-5, one lane in each direction will be closed at I-5 during the daytime.

 