Imperial Highway & Pioneer Blvd. Project – March 22 – March 29, 2019

Construction on this project is 87% complete.
Open to traffic: *Early summer 2019. 

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

There are no lane closures scheduled for this week. 

Construction of this interchange is nearing completion. The contractor is finalizing construction along Imperial Highway and Norwalk Blvd. at the I-5 interchanges. Within the next several weeks, final concrete will be poured for the remaining lanes of the reconstructed interchanges at Imperial Highway and Norwalk Blvd. 

If crews work on Imperial Highway, Norwalk Boulevard and Pioneer Boulevard at I-5, one lane in each direction may be closed on each street with traffic control during the daytime, between 8:30 a.m. and 3:30 p.m.