HOLIDAY CLOSURE SCHEDULE
In observance of the Thanksgiving holiday there will be no closures scheduled Wednesday, Nov. 25 through Sunday, Nov. 29.
Adoree Street has been opened to through traffic between Imperial Highway and Norwalk Boulevard.
Pile driving activity is underway at Pioneer Boulevard and will be conducted weekdays between 8:30 a.m. and 3:30 p.m.; this work will be ongoing for approximately two weeks.
Crews have begun CIDH (cast in drilled hole) activities on Mondon Avenue, between Tina Street and Bayla Street. This work involves drilling holes in the ground to prepare the retaining wall foundations, as part of planned roadway improvements as part of the I-5 Improvement project.
Access on Mondon Avenue is temporarily limited to local traffic only, for approximately the next 10 weeks, as crews work to complete improvements in this area. This work will be conducted weekdays between 7 a.m. and 3:30 p.m. For the safety of the public and work crews, “No Through Traffic” signs will be posted on Mondon Avenue at the intersections of Bayla Street and Tina Street.
As crews erect falsework at Imperial Highway at I-5, one lane of Imperial Highway will be closed at I-5 during the daytime. In addition crews will be working to install wooden beam at Norwalk Boulevard / San Antonio Drive at I-5; lanes may be reduced while this work is being conducted.