Pile driving activity at Imperial Highway has been partially completed. Pile driving activity at Pioneer Boulevard is underway. This work will be conducted weekdays between 8:30 a.m. and 3:30 p.m. through Monday, Oct. 26. Once pile driving is completed at Pioneer Boulevard, the contractor will move back to Imperial Highway.
Construction of the concrete barrier separating Union Street and the new Southbound Frontage Road has been completed. On Wednesday, Oct. 28 crews will be conducting paving operations on Union Street, between Paddison Avenue and San Antonio Drive. In order to complete the final paving, Union Street will be closed to all traffic between 7 a.m. and 3:30 p.m. Temporary “No Parking” signs will be posted at least 48 hours in advance of this activity. These signs will be marked with the date and times of the parking restriction. Residents are reminded that this work will be performed early in the morning and are advised not to park on Union Street the night before. Vehicles parked on Union Street during the parking restriction may be towed, at the owner’s expense, to allow the paving work to proceed.
Additional paving activity on Norwalk Boulevard / San Antonio Drive is scheduled Thursday night, Oct. 29. This work will require a complete closure of Norwalk Boulevard / San Antonio Drive, between Olive Street and Adoree Street, from 9 p.m. Thursday, Oct. 29 to 5 a.m. Friday, Oct. 30. Changeable message signs and detour signs to notify the public and direct traffic will be placed in the field in advance of this work. The closure area is shown on the map below in red; the detour route is highlighted in blue.
For additional information regarding this work, please visit the project Google map below.