IMPERIAL HIGHWAY & PIONEER BOULEVARD PROJECT – Week of Sept 24, 2017

Crews will continue pile driving at Norwalk Boulevard / San Antonio Drive bridge; this work will be conducted weekdays between 7 a.m. and 3:30 p.m. and will be ongoing intermittently for approximately the next five weeks. Please be advised this work may be loud and disruptive due to equipment noise, vibration and pounding related to pile driving activity. 

Sunday, Sept. 24 through Thursday, Sept. 28, the contractor will be performing falsework operations and column work nightly between 9 p.m. and 6 a.m. and will close southbound Pioneer Boulevard to traffic between Crewe Street and Imperial Highway.

The closure area is shown in red on the map below; the detour route is highlighted in green. Unless otherwise noted, work will be performed between 9 p.m. and 6 a.m.

 

As crews work on Imperial Highway, Norwalk Boulevard and Pioneer Boulevard bridges at I-5, one lane in each direction will be closed on each street (at I-5) during the daytime, between 8:30 a.m. and 3:30 p.m.

This information can also be found in the Google map below.

 