Construction on this project is 87% complete.
Projected date of completion: Late 2018. 

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

Construction of the retaining walls along the Norwalk Blvd. on ramp to northbound I-5 continues.  The lane shift on Norwalk Blvd. northeast of the San Antonio Bridge is complete and reconstruction of the median is in progress.

We have been pouring concrete for new lanes on I-5 from south of Norwalk Blvd. to north of Imperial Highway for several weeks.  Photos below from north of Imperial Highway are from September 18. (Tap / click on photos for slide show and details):

 

Traffic lanes on Norwalk Blvd. were shifted to allow reconstruction of the median northeast of the San Antonio Bridge. Photos below from September 4 and September 11:

 

As crews work on Imperial Highway, Norwalk Boulevard and Pioneer Boulevard bridges at I-5, one lane in each direction may be closed on each street (at I-5) during the daytime, between 8:30 a.m. and 3:30 p.m.

 