IMPERIAL HIGHWAY & PIONEER BOULEVARD PROJECT – Week of September 25, 2016

Construction crews are clearing vegetation, forming retaining walls, and moving construction equipment along Spry Street and Arlee Avenue. This work will be conducted weekdays between 7 a.m. and 3:30 p.m. and will be ongoing for approximately three months. Residents are advised to take precautions to ensure pedestrian and roadway safety. Please be advised, work may be noisy due to construction equipment moving on- and off-site, truck back up alarms, and other construction related noise.

Crews will be placing new rock blanket at the following intersections:

  • Adoree Street and Imperial Highway
  • Kalnor Avenue and Imperial Highway
  • Union Street and Paddison Avenue
  • Imperial Highway and S. Frontage Road

Crews will be performing landscaping and paving activities along Mondon Avenue between Gem and Pluton Streets. This work will be conducted Monday through Friday, between 7 a.m. and 3:30 p.m.

Retaining wall work adjacent to northbound I-5, near Norwalk Boulevard, will be ongoing for the next four weeks. Work will be conducted during the day, Monday through Friday, between 7 a.m. and 3:30 p.m.

Also, a concrete barrier will be installed on both northbound and southbound I-5, just south of the Orr and Day bridge by the Union Pacific railroad tracks. The contractor will also be placing block wall on northbound I-5 just south of Orr and Day Road.

As crews work on Imperial Highway, Norwalk Boulevard and Pioneer Boulevard bridges at I-5, one lane in each direction will be closed on each street (at I-5) during the daytime, between 8 a.m. and 3 p.m.