The week of April 24, crews will pour the approach slabs for the new Bloomfield Avenue Bridge.

In addition to this work, crews will begin releasing falsework (the temporary bridge support structures) on the Rosecrans Avenue bridge. This will require nightly closures of Rosecrans Avenue to through traffic in both directions underneath I-5, between 9 p.m. and 5 a.m., Monday, April 25 and Tuesday, April 26. The closure area is highlighted below in red; motorists will be directed to follow the detour route highlighted on the map below in green.  For detailed detour information, please visit the project Google map.

Work area is highlighted in red; local access will be maintained for residents and businesses off Bloomfield Avenue and Firestone Boulevard.No access to Rosecrans Avenue underneath I-5 freeway. Rosecrans Avenue I-5 on and off-ramps will also be closed while this work is completed. Motorists will be directed to follow the detour routes highlighted in green, to bypass the closure area

Work area is highlighted in red; local access will be maintained for residents and businesses off Bloomfield Avenue and Firestone Boulevard.No access to Rosecrans Avenue underneath I-5 freeway. Rosecrans Avenue I-5 on and off-ramps will also be closed while this work is completed. Motorists will be directed to follow the detour routes highlighted in green, to bypass the closure area.

Finally, in order to move a crane into the work area, crews will need to close either northbound or southbound lanes of I-5, at night sometime in the next two weeks (week of April 24 or May 2). This work has not yet been scheduled, but more information will be provided as soon as it is available.