Valley View Ave. Interchange Project – December 7 – December 14, 2018

Construction on this project is 33% complete.

Projected dates:
Completion of first half of Valley View Ave. Bridge: Revised to *late 2019.
Completion of second half of Valley View Ave. Bridge: Revised to *late 2021.
Completion of entire I-5 Valley View Ave. Interchange project: Revised to *late 2021.

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

Scheduled road closures for next week:
1. S. Firestone Blvd. is scheduled to be closed from Marquardt Ave. to the Valley View Ave. Bridge on Sunday, Dec. 09 for paving of a new detour. Only local businesses within the closure will be permitted from 6 p.m. to 9 p.m. The road will be closed to all from 9 p.m. to Sunday, Dec. 09 until 6 a.m. Monday, Dec. 10.

S. Firestone Blvd. will close again from 9 p.m. Thursday, Dec. 13 until 6 a.m. Friday, Dec. 14 to stripe and to switch traffic. When S. Firestone Blvd. re-opens, traffic will utilize the new detour.

2. Southbound I-5 between Valley View Ave. and Artesia Blvd. is scheduled to be reduced to one lane to place K-rail and crash cushion from 11:59 p.m. Monday, Dec. 10 until 5 a.m. Tuesday, Dec. 11. On and off ramps will remain open.

3. Valley View Ave. is scheduled to be closed in both directions from Alondra Blvd. to Arbor Pl. for signal relocation and pothole repair from 9 p.m. Tuesday, Dec. 11 until 6 a.m. Wednesday, Dec. 12. Traffic will not be able to access Firestone Blvd. from Valley View Ave., but traffic will be able to turn right onto Valley View Ave. from Firestone Blvd. Local businesses will be permitted access at all times.

 

Grading and compacting are complete for the section of ground that will support the third (middle) section of the first half the Valley View Ave. Bridge. Workers have been delivering supplies to assemble falsework (temporary structure support). Photos below from December 4:

 

 

Construction of retaining walls for the new southbound Firestone Blvd. where it will connect to Valley View Ave. in La Mirada continues. Concrete forms are placed over rebar frame in preparation for concrete pour. Photos below from November 13 , 20 and 27:

 

At the Coyote Creek Bridge in La Mirada, the concrete abutment walls are complete. Photos below from November 13, November 27, and December 4 show the progress:

 

Construction of the pier walls that will support the new bridge over Coyote Creek, east of I-5 near Trojan Way in La Mirada, is complete. The bridge will carry the new lanes of I-5 and N. Firestone Blvd.  Photos below:

 

Grading and curb installation is complete for a temporary detour to Firestone Blvd. near the Valley View Ave. Bridge west of I-5. Grading and compacting continue where the Valley View Ave. off ramp from southbound I-5 and the southbound Firestone Blvd. ramp will connect to the bridge. Photos below from November 27:

 

The final layer of concrete has been poured on the surface of the Valley View Ave. Bridge over Arbor Place and west of I-5 in Cerritos. Photos below from October 2:

DISCLAIMER: Due to the dynamic nature of construction, please note that all dates and times are subject to change due to unforeseen operational factors or inclement weather.