Valley View Ave. Interchange Project – February 26, 2021 – March 5, 2021

Construction on this project is 75% complete.

Projected dates:
The first half of Valley View Ave. Bridge opened to traffic on Monday, October 7, 2019 with one lane in each direction. A second lane opened to traffic on the southbound side of the Valley View Avenue Bridge on Friday, September 18, 2020. 

Completion of second half of Valley View Ave. Bridge: Revised to *mid-2022.
The new Valley View Ave. off ramp from southbound I-5 opened on September 19, 2020.  
N. Firestone Blvd. reverts to two lanes in each direction east of Valley View Ave.: End of 2021. 
N. Firestone Blvd. re-opened between Knott Ave. and Trojan Way on February 28, 2021.  
New S. Firestone Blvd. running under the Valley View Ave. Bridge opened on July 13, 2020. 
New S. Firestone connector ramp to the Valley View Ave. Bridge opened on February 28. 2021. 
I-5 Valley View Ave. Interchange projected date of completion: Revised to *mid-2022.

*Update:
To adjust city water valves, N. Firestone Blvd. is scheduled to close between Artesia Blvd. and Knott Ave. and Valley View Ave. is scheduled to close between N. Firestone and Alondra Blvd. from 9 p.m. to 6 a.m. the night of Wednesday, March 3.

Local business access will be permitted at all times. If possible, traffic will be controlled by flagging, rather than closing the roadway. Work will probably be completed and the roads reopened within three hours.  


1. The new S. Firestone connector ramp to the Valley View Ave. Bridge is now open to traffic. There is a stop sign at the intersection with the Valley View Avenue Bridge. This will allow traffic to connect from Alondra Boulevard / Marquardt Avenue directly to Valley View Avenue. This will also allow traffic to exit southbound I-5 at the Valley View Avenue off ramp; turn right onto Valley View Avenue; and turn right again onto S. Firestone Boulevard to access businesses between Marquardt Avenue and Artesia  Boulevard.  Photo of location below. See green arrows:

2.  The new N. Firestone Boulevard is now open to traffic between Knott Avenue and Trojan Way. There is a stop sign southbound on Knott Avenue at N. Firestone Boulevard. Map below:

 

3. There is now a second lane open to traffic on northbound Valley View Avenue between N. Firestone Boulevard and Alondra Boulevard. Intersection traffic is controlled by permanent signals. Map below:


Workers  have been constructing rebar frames for stem walls and covering them with wooden forms in advance of pouring concrete along the deck of the middle section of the second half of the Valley View Avenue Bridge. Concrete has been poured on the south end of the bridge. Video and photos below from February 24:

A view of concrete poured for new lanes on I-5 southeast of the Valley View Avenue Bridge below:

More video of rebar mat on soffit of middle section of second half  bridge from early February below:

 

 