Valley View Ave. Interchange Project – June 21- June 28, 2019

Construction on this project is 43% complete.

Projected dates:
Completion of first half of Valley View Ave. Bridge: Revised to *late 2019.
Completion of second half of Valley View Ave. Bridge: Revised to *late 2021.
Firestone Blvd. reverts to two lanes in each direction at Valley View Ave.: End of 2021. 
I-5 Valley View Ave. Interchange projected date of completion: Revised to *End of 2021.

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

Closures CANCELLED for the nights of Wednesday, June 26 and Thursday, June 27:
Southbound Valley View Ave. from Alondra Blvd. to Artesia Blvd. 
Northbound Valley View Ave. from Arbor Place to Alondra Blvd. 
N. Firestone Blvd. from Gateway Dr. to Valley View Ave.  

*Update: 
The following overnight closures are scheduled to pave new freeway lanes:

From 11:00 p.m. Thursday, June 27 until 5 a.m. Friday, June 28:
Westbound 91 (Artesia Freeway) connector to northbound I-5 closed.

From 11:59 p.m. Thursday, June 27 until 5 a.m. Friday, June 28:
I-5 all northbound mainline lanes and corresponding on and off ramps closed from Aresia Blvd. to Valley View Ave.

Detour signs will direct traffic off northbound I-5 onto westbound Artesia Blvd. to northbound Carmenita Rd. to rejoin northbound I-5 at the Carmenita Rd. on ramp.

Alternate route: westbound State Route 91 (Artesia Freeway) to northbound I-605 (San Gabreil River Freeway) to northbound I-5.

Confirm the lane closures in real time at http://quickmap.dot.ca.gov/ .Also watch for updates at twitter.com/My5LA. Detour map below:

 

Click to view videos of work in progress on I-5 Valley View Av. Bridge from June 11 below:

View of the future Valley View off ramp from southbound I-5. Panning south towards the new Valley View Ave. Bridge. This is the falsework, or temporary frame structure support, over which the ramp will be constructed. View from below, from June 11 and June 18:

View from above, June 18:

View of Valley View Ave. Bridge panning toward I-5. Workers are laying lumber forms horizontally to create a base over which another layer of rebar will be secured. June 18, below:

Future Firestone Blvd. ramp panning towards bridge. Workers making final preparations on Tuesday, June 18 for the concrete pour that occurred that night:

Concrete has been poured over the “soffit” (deck underside) and inside the rebar frames of the stem walls on the Valley View Ave. Bridge. Workers are now building frames and laying the same forms horizontally as a base to place another layer of rebar. Photos below from June 5, June 11, and June 18:

On the future Firestone Blvd. ramp to the Valley View Ave. Bridge, workers installed rebar on the “soffit” (underside of the deck) and the stem walls. Then they secured lumber forms to the stem walls in preparation for a concrete pour that occurred the night of Tuesday, June 18. Photos below from May 14 through the day of final preparations on June 18:

And photos from the night of the concrete pour, Tuesday, June 18: 

Workers are now building the “falsework” (temporary frame support structure) for the future Valley View Ave. off ramp from soutbound I-5 that will connect the ramp an support columns to the deck of the bridge. Photos below from June 11 and June 18:

In La Mirada, the contractor is constructing new lanes of northbound I-5 between Knott Ave. and north of Trojan Way near the new Coyote Creek Bridge. The first layer of concrete (lean concrete base) is complete and the final layer of concrete will be poured the week of  June 24. Photos below from June 5 and June 18: