Valley View Ave. Interchange Project – November 22- November 29, 2019

Construction on this project is 50% complete.

Projected dates:
Completion of first half of Valley View Ave. Bridge: Open to traffic Monday, October 7, 2019.
Completion of second half of Valley View Ave. Bridge: Revised to *late 2021.
N. Firestone Blvd. reverts to two lanes in each direction at Valley View Ave.: End of 2021. 
N. Firestone Blvd. re-opens between Knott Ave. and Trojan Way: by the end of 2019. 
I-5 Valley View Ave. Interchange projected date of completion: Revised to *end of 2021.

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

S. Firestone Blvd. is scheduled to be closed from Marquardt Ave. to the on ramp to southbound I-5 from *8 p.m. Thursday, Nov. 21 until 6 a.m. Friday, Nov. 22. To remove falsework from the completed first half of the bridge. Access to businesses within the closure will be permitted.  

The steel girders, rebar, and concrete from the demolished second half of the Valley View Ave. Bridge have been removed for recycling. Workers are now removing falsework (temporary frame support) from the completed first half of the bridge. Videos below show progress from Nov. 11 to Nov. 19:

Photos below from Nov. 19:

The contractor is constructing the foundation for abutment wall and placing forms over the retaining walls for the Firestone Blvd. ramp where it will connect to the second half of the Valley View Ave. Bridge. Videos below from November 11 and November 19:

Photos below from November 19:

Photos below show construction of abutment wall for Valley View Ave. on ramp where it will connect to southbound I-5 from Oct.22 through Nov. 19:

Earth mover clearing debris from work site on Nov. 19:

 

Demolition of the second half of the old Valley View Ave. Bridge is complete. Photos below from before removal of steel girders and after:

 